Microsoft exits Nscale’s £2bn Essex AI data centre project amid power concerns

Written by Tue 20 Oct 2026

Electricity transmission pylon and power lines with battery icons and digital overlays, representing grid infrastructure and energy storage technology.

Microsoft has withdrawn from Nscale’s planned £2 billion ($2.6 billion) AI data centre in Loughton, Essex, following delays to the site’s power supply.

As first reported by The Telegraph and subsequently by the BBC, the technology giant has ended its involvement in the project, which had been promoted as the UK’s largest AI supercomputer.

The facility had been expected to receive power by the end of 2026. However, reports indicated that a grid connection may now be unavailable until the 2030s.

Nscale said it remained committed to the development and was investigating alternative sources of power.

“We remain committed to both the Loughton project and the UK, and we are exploring alternative power sources for the site, in addition to other expansion sites in the UK,” said an Nscale spokesperson.

The company added that its relationship with Microsoft remained “strong and long-term”, with the two businesses continuing to work together on projects in Norway, Portugal and the US.

“This unfortunate London-wide grid issue has no impact on our other contracts,” Nscale told the BBC.

Grid Delays Threaten Nscale Data Centre Plans

Nscale announced its partnership with Microsoft in September 2025, outlining plans to deliver 50MW of AI computing capacity at Loughton, expandable to 90MW.

The site was expected to house 23,040 NVIDIA GB300 GPUs, with delivery scheduled for the first quarter of 2027.

The infrastructure was intended to support Microsoft’s Azure cloud services and formed part of wider investment commitments to expand the UK’s domestic AI computing capacity.

At the time, Josh Payne, CEO of Nscale, described the development as important to the UK’s technological competitiveness.

“This historic commitment from Nscale shows how the UK can build the future of AI, together with our partners from the US. It’s only by building world-class AI infrastructure that we will stay competitive in the global race,” said Payne.

The subsequent power delays have exposed the difficulties of delivering large-scale AI infrastructure within the proposed timetable.

Although Nscale has continued to pursue the development, Microsoft’s withdrawal leaves the company facing uncertainty over the site’s future customer arrangements.

Power and Connectivity Raise Infrastructure Concerns

Lee Myall, CEO of Neos Networks, said the reported withdrawal highlighted the challenges facing the UK’s AI infrastructure ambitions.

“Microsoft’s reported withdrawal from Nscale’s planned data centre in Loughton, Essex, is a reminder of the infrastructure challenges facing the UK’s AI ambitions. AI is developing at pace, but traditional routes to securing the power needed for new data centres can take years. Unless the UK can build the underlying infrastructure more quickly, there is a risk that its ability to scale AI will not keep up with demand.”

Myall also argued that electricity availability should be considered alongside the wider infrastructure required to operate AI data centres.

“Power availability is clearly the immediate challenge, but it should prompt a broader conversation about the infrastructure AI depends on. As well as power and land, connectivity needs to be considered early in decisions about where data centres are located.”

According to research commissioned by Neos Networks, 92% of surveyed enterprises said local connectivity availability influenced where they deployed or expanded AI workloads.

Myall said high-capacity networks were essential to connecting data centres with the cloud platforms and businesses relying on their computing resources.

“The UK has an opportunity to get this right as AI scales, by planning power and connectivity together and making better use of existing infrastructure. Taking a more joined-up approach will help ensure investment in AI delivers lasting benefits to more regions and communities.”

Grid Constraints Extend Beyond Loughton

The complexity of delivering electricity infrastructure is also prompting changes to how major projects are managed. National Grid’s Strategic Infrastructure team is digitising its capital project delivery processes through a partnership with Method Grid, bringing standards, approvals and project controls into a common environment.

The Loughton development has illustrated the consequences of infrastructure delivery falling behind investment commitments.

Electricity availability has also complicated data centre development elsewhere in Europe. Google recently secured approval for its Dublin data centre expansion after overturning an earlier planning refusal that cited insufficient grid capacity and a lack of significant on-site renewable generation.

Nscale’s original plans established the scale of the proposed computing capacity, but the reported grid delays have left its delivery timetable uncertain.

With Microsoft withdrawing from the project, Nscale must now establish how the facility can secure sufficient electricity and attract customers willing to commit to the site.

The outcome will also carry implications for the UK’s wider ambitions to expand domestic AI infrastructure, where access to power remains a critical constraint on development.

Join Data Centre World Paris

18 - 19 November 2026, Porte de Versailles, Paris

Balancing power, capacity and responsibility in digital infrastructure.

Meet data centre operators, infrastructure leaders, and engineers exploring energy efficiency, AI-ready capacity, cooling, resilience, and operations in a market shaped by cost, sustainability and scale.

 

Written by Tue 20 Oct 2026

Tags:

AI infrastructure grid capacity Microsoft Nscale nvidia power availability
Send us a correction Send us a news tip


Subscribe for News in Your Inbox